Sewer-Main Collection Pipe Joint
Infiltration Testing and Life Cycle Cost Analysis
Sully Curran P. E. Executive Director
Fiberglass Tank & Pipe Institute
ABSTRACT
Research Projects
Major members of the sewer-main pipe manufacturing industry and the University
of Houston have completed and published the results of the following two
research projects:
- The Sewer-Main Collection
Pipe Joint Infiltration Testing research project that measured the water
infiltration rate of water-tight designed 30-inch pipe joints. The joint
tightness testing was conducted at a minimum hydrostatic head of 15 feet
(i.e., 7 psi) under axial, shear loaded and angularly deflected conditions.
- The Life Cycle Cost Model
research project developed an interactive model to estimate the costs of
constructing, rehabilitating, operating and maintaining sewer mains under
various infiltration levels over a 30-year life. The model has been
calibrated with published data and may be used to compare different
rehabilitation and maintenance scenarios to identify the most cost effective
sewer main design.
Infiltration Infrastructure
Damage
Ancillary costs such as infrastructure damage (e.g., roadway settlement, sink
holes) are not included in the Life Cycle Cost Model and may be factored in from
local conditions. As an example of potential infrastructure damage, this paper
includes a case study showing the impact of joint infiltration in the city of
Houston.
Project Costs and Funding
The two research projects were funded by participating industry members and the
Environmental Protection Agency Office of Wastewater through a grant to, and
administered by, the Fiberglass Tank & Pipe Institute. Fourteen Steering
Committee members contributed some $50,000 and over 2,000 professional man-hours
to the project from 2000 through 2003. This includes the cost of pipe joint
testing paid for by the manufacturers and time attending a series of daylong
meetings. By applying a value of $125 per hour for these professional services,
industry’s total contribution is some $300,000 plus the $100,000 EPA grant for a
total project cost of $400,000.
Report Availability
The Sewer-Main Collection Pipe Joint Infiltration Testing research
results consist of four reports, each of which describe the testing of
participating pipe trade association member company products, namely the
American Concrete Pipe Association, Fiberglass Tank & Pipe Institute, National
Clay Pipe Institute and Uni-Bell PVC Pipe Association.
The Life Cycle Cost Model research report consists of a description of
the model, default input data derived from an international literature search
and an interactive model that may be downloaded and used by municipal or
consulting design engineers.
The foregoing research project reports are available on the internet by
searching for “cigmat” which will bring up the “Cigmat Homepage.” Under this
homepage heading will be the heading “Research Report.” Click on Research Report
to display each of the five reports in alphabetical order. Each report shows a
list of individual report sections (i.e., Front Page, Preface, Table of
Contents, Report and Appendices). The Life Cycle report list includes
instructions for using both the model and the interactive model to be downloaded
by the user.
KEYWORDS
University of Houston, pipe joint, infiltration, infrastructure, life cycle
cost, , model, angular deflection, shear load, Environmental Protection Agency,
sewer overflow, Almeda
INTRODUCTION
Fiberglass Tank & Pipe Institute
The Institute was incorporated in 1987 as a non-profit trade association serving
the major fiberglass piping, manhole, septic tank and oil/water separator
manufacturers in the USA. The Institute provides a forum through which industry
members can work together effectively toward common goals. This includes
coordinating studies, combining resources to provide standard-setting
organizations with superior technical data and disseminating information to the
government, industry and the public.
BACKGROUND
The September 23, 1997 US Environmental Protection Agency (EPA) report to
Congress (The 1996 Clean Water Needs Survey) identified a need for the
construction of new and rehabilitation of existing sewers to control sewage
overflows resulting from premature piping failures (i.e., infiltration) and
higher demand. As a result, we have seen much new construction and
rehabilitation that has been funded under the State Revolving Fund provisions of
the Clean Water Act.
Municipal entities are surveying their needs and considering various
construction methods (e.g., open trench, no-dig) and materials (e.g., clay,
concrete, ductile iron, fiberglass, PVC, polyethylene, steel) to upgrade sewer
collection systems. The resulting capital projects are being evaluated and
prioritized for federal funding. However, the project development process should
provide those who implement the CWA with a method to evaluate the life cycle
cost of the construction alternatives for sewer mains (i.e., excluding laterals)
in different areas of the United States. This methodology would provide a means
of comparing construction alternatives and the selection of the most
cost-effective long-term installation.
Project Funding and Participation
The Fiberglass Tank & Pipe Institute was awarded a $100,000 EPA Grant to serve
as seed money and develop a life cycle model to address sewer main pipe joint
infiltration costs. The University of Houston (UH) Department of Civil and
Environmental Engineering was selected by the Institute as the research
contractor. During the development phase of the project UH determined that,
while ASTM standards existed for certain joint infiltration leak rate tests,
these standards were not universally applicable to all pipe materials or joining
methods. Further, leak test data was generally not available for joints that
were subjected to underground installed axial, angular deflection and shear
stress conditions. Thus, there was a need to develop a universal test method,
conduct comparable leak rate tests and develop test data as input to the life
cycle cost models. Therefore, UH research was conducted on two projects namely,
Sewer Main Pipe-joint Infiltration Leak Rate Testing and a Sewer Main
Collection System Infiltration Life Cycle Cost Model.
Invitations to participate in the project were made to all large diameter (i.
e., 30-inch and larger) sewer-main pipe manufacturers and trade associations.
While certain trade associations declined, the following four trade associations
participated in the project:
- American Concrete Pipe
Association
- Fiberglass Tank & Pipe
Institute
- National Clay Pipe Institute
- Uni-Bell PVC Pipe
Association
The project moved forward as a
cooperative research project funded by the Environmental Protection Agency
Office of Wastewater and the foregoing four trade associations. Each trade
association contributed technical manpower to assist UH during the joint testing
phase and reimbursed UH for each joint test. In addition, the trade associations
funded legal filings, committee meeting room and other costs incurred during the
three-year project life to ensure full participation of interested parties.
RESEARCH STEERING COMMITTEE
A Steering Committee was formed and consisted of 14 members from industry,
academia, EPA Office of Wastewater and chaired by Mr. J. E. Pate, Pate Engineers
Inc. of Houston, Texas. Industry was represented by the four trade associations;
public users by four cities (Houston, Victoria and Conroe in Texas and
Montgomery, Alabama); Professional technical input came from three engineering
companies, UH and a major underground pipe installation contractor. Project
administration was provided by the Institute which developed the following to
ensure project equity and credibility:
- Confidentiality Agreement
executed by Steering Committee members.
- Federal Trade Commission and
Department of Justice notification under the national Cooperative Research
and Production Act of 1993.
This Steering Committee provided
oversight of the University of Houston (UH) research projects including:
- Meeting three to four times
per year at the UH testing facility for on-site updates on UH research
project status.
- Providing overall UH
research project guidance and recommendations that helped achieve project
goals.
- Reviewing and developing
Steering Committee consensus approval of the infiltration test protocols
developed by the Civil & Environmental Department of the University of
Houston for pipe joints.
- Determining through
laboratory controlled testing, the infiltration leak-rates for large
diameter sewer main pipe joints.
- Developing an interactive
life cycle cost model for different infiltration rates of large diameter
sewer main collection system joints and costs incurred as a result of
infiltration over the life of the system.
- Reviewing draft UH project
task reports, offering comments and developing a Steering Committee
consensus approval before final reports were released.
The following membership of the
Steering Committee provided a balance of producers and non-producers (i.e.,
users, governmental, those with expertise):
|
Organizations |
Representatives |
| US
EPA Office of Wastewater |
Charles P. Vanderlyn |
|
University of Houston |
Dr. C. Vipulanandan |
|
City of Houston, Texas |
Henry N. Gregory |
|
City of Victoria, Texas |
Kenneth E.Gill |
|
City of Conroe , Texas |
Brent Sherrod |
|
City of Montgomery, Alabama |
Danny Holmberg |
|
Laughlin-Thyssen (HCA contractor) |
Clifford L. Tubbs |
|
Parsons Brinckerhoff (Design Engineers) |
Richard Thomasson |
|
Black & Veatch (ASCE Representative) |
Rick Nelson |
|
Pate Engineers (Design Engineers) |
J.
E. Pate |
|
American Concrete Pipe Association |
Matthew S. Childs |
|
Fiberglass Tank & Pipe Institute |
Richard C. Turkopp |
|
National Clay Pipe Institute |
Ed
Sikora |
|
Uni-Bell PVC Pipe Association |
Shah Rahman |
SEWER MAIN PIPE-JOINT
INFILTRATION LEAK RATE TESTING
Objectives
The overall objective was to determine, through controlled laboratory testing,
the infiltration leak-rates for different types of 30-inch diameter sewer
pipe-joints under various loading conditions. The specific objectives were as
follows:
- Develop a testing protocol
to determine the infiltration at the pipe-joint under the following test
conditions:
- Straight joint (i.e., axial)
- Angular deflection
- Shear load
- Develop a testing facility
to perform the tests under external hydrostatic pressure equivalent to 15
feet of water (i.e., 7 psi).
- Perform tests according to
the testing protocol on pipe joints assembled by the pipe manufacturing
representatives.
Testing Program
Two instrumented test stands were designed and constructed at the University of
Houston. Each test stand was capable of accommodating two three-foot lengths
(i.e., six feet) of 30-inches or greater diameter pipe joined together for
testing. Provisions were made to constrain the pipe from moving laterally. The
loading points were instrumented with 20,000 pound load cells to measure the
applied and reaction loads. Test stand provisions also allowed the pipe-joint to
be tested under deflection and shear load in accordance with the test protocol.
Two sets of pipe-joints were first tested under no load and then the same
pipe-joints were tested by first shear and then angular loading tests (i.e., 7
psi).
The test protocol required that the manufacturer joint designs and
configurations tested had a history of successful field service for a minimum of
two (2) years before January 1, 2000. the intent was to not test new or
innovative pipe-joint designs, but instead those that should be available in the
market place. In each case the specific joint designs and configurations
submitted by the manufacturers demonstrated that these materials and joint
designs should withstand a hydrostatic head of 15 feet of water without
infiltration leakage.
LIFE CYCLE MODEL
Objectives
The objective of this study was to develop a model that may be used by design
engineers to estimate the Life Cycle Cost (LCC) for constructing, operating and
maintaining a wastewater sewer system. The specific objectives were as follows:
- Identify the important
parameters that influence the cost of constructing and maintaining a
wastewater system with infiltration.
- Develop a LCC model spanning
a period of 30 years.
- Quantify the major
components (i.e., length of pipes, number of manholes, size of treatment
plants) of the wastewater system.
- Incorporate certain
maintenance and rehabilitation methods for various sizes of wastewater
systems with changing populations and identify the most cost effective plan.
Model Development
The basic spreadsheet model has been developed to quantify daily infiltration
caused by rainfall and/or groundwater based on population and average household
occupancy. This model is capable of estimating the sizes of various components
of a wastewater system based on default settings derived from new databases.
International Database Search
The new databases were derived from an international literature search,
information on population, pipe lengths, number of treatment plants, number of
lateral connections, average annual daily flow (mgd), pump station horse power
(hp) and the treatment costs obtained from various cities across the United
States. While a correlation was observed between various system characteristics
to identify the model default settings, they may be reset by the user based on
own experience, new or local data.
Major Model Components
Input spread sheet: Users of the model will enter variable data whereas
default values are provided and may be used. Input values include such variables
as population, number/type of establishments, manhole spacing, wastewater
treatment cost. For example, the joints in pipeline are classified in three
categories. Lateral-Main joints (joints at the intersection of lateral with main
line sewer), Mainline joints (joints between the pipes of the mainline sewer)
trunk line joints (joints between the pipes of the trunk sewer). The default
spacing is 20 feet. The user can change the spacing as per their system.
Capital cost: The capital cost sheet shows the cost associated with
laying out a wastewater system of the size obtained in the basic model sheet.
5-year Outlook: There are 5-year model predictions based on incorporating
the change in population every 5 years and one percent increase in system
infiltration every year.
Sanitary Sewer Overflow Outlook: The model helps to check when the system flow
exceeds the treatment plant capacity and the prescribed regulations of EPA for
excessive infiltration (average dry weather flow not exceeding 120 gpcd-gallons
per capita per day).
Rehabilitation Cost: Rehabilitation is performed every 10 years cycle.
Rehabilitation is performed on 10% of the system. The cost calculation is done
as per rehabilitation costs provided by the user (default values are also
provided). 30 years rehabilitation cost is calculated based on two
rehabilitation cycles.
Life Cycle Cost: The Life Cycle Cost sheet provides the cost of
wastewater treatment for 30 years when system rehabilitation is performed every
10 years. An alternate Life Cycle Cost is also determined for no rehabilitation
on the system. Thus the difference in the life cycle cost with maintenance and
no maintenance is obtained.
RESEARCH REPORTS AND MODEL AVAILABILITY
The research reports may be downloaded from the internet and should provide
municipal and consulting design engineers with the tools to compare infiltration
tightness of available pipe-joint materials/methods and the model to determine
life cycle costs for sewer main projects. The foregoing research project reports
are available on the internet by searching for “cigmat” which will bring up the
“Cigmat Homepage.” Under this homepage heading will be the heading “Research
Report.” Click on Research Report to display each of the five reports in
alphabetical order. Each report shows a list of individual report sections
(i.e., Front Page, Preface, Table of Contents, Report and Appendices). The Life
Cycle report list includes instructions for using both the model and the
interactive model to be downloaded by the user.
CASE STUDY: JOINT INFILTRATION AND INFRASTRUCTURE DAMAGE
Almeda Road, Houston, Texas
It started as a typical urban pothole on Almeda Road in Houston, but by 2002 the
hole grew to 40 x 60 feet – a cave-in big enough to swallow a full sized car.
The sinkhole closed the road and rerouted traffic for months while the city
assembled a team of consulting engineers and contractors to assess soil
conditions an effect pipeline replacement. and cost the city of Houston $10
million to repair.
Almeda Road Sewer Line Failure
The 84-inch sewer line along Almeda road was originally installed in 1978. It is
some 40 feet below grade and 30 feet below the water table. Years of groundwater
infiltration weakened the native soil and in 1991, 330 feet were replaced. Later
by 1994, much of the pipe was internally or externally grouted in an effort to
extend the life of the pipeline. However, after years of groundwater
infiltration smaller cracks grew into larger cracks, weakening the pipe bed and
caused a nearby waterline break. Ultimately, the affected area caused the
closing of the four-lane heavily trafficked street.
Sewer Line Replacement and Cost
Ground-penetrating radar was used to determine where the soil strength was
compromised and soil grouting was required to provide bedding for the
replacement pipe. In addition, 28,000 feet of existing interceptor piping was
inspected by closed circuit television. The area adjacent to the sinkhole was
stabilized, dewatered and a liner plate shaft constructed. Fiberglass 72-inch
diameter pipe with 46 psi stiffness was used to slipline three sections
including 1,700, 360 and 370 feet. Direct bury 72-inch pipe was installed in the
location of the sinkhole for a total replacement of 2,500 feet. All pipe joints
were gasket sealed to be leak free and prevent future infiltration. The Almeda
sewer line infiltration failure cost the city of Houston $10 million to repair.
SUMMARY
Sewer-Main Collection Pipe Joint Infiltration
The sewer-main pipe industry and University of Houston completed the pipe joint
infiltration research project to measure the water infiltration rate of 30-inch
pipe joints at a minimum hydrostatic head of 15 feet (i.e., 7 psi) under axial,
shear loaded and angularly deflected conditions. The project was funded by
participating industry members and the Environmental Protection Agency Office of
Wastewater through a grant to, and administered by, the Fiberglass Tank & Pipe
Institute. The research project determined that certain pipe joints designs
submitted by concrete, fiberglass, clay and PVC trade associations for leak
testing under a 15 foot hydrostatic head did not leak under axial, shear load
and deflection conditions. Design engineers may use the test reports to specify
the use of such pipe joints to minimize infiltration leakage in new and
rehabilitation projects.
Life Cycle Cost Model
Certain members of the sewer-main pipe industry and University of Houston
completed the infiltration life cycle cost model research project, which was
designed to estimate the costs of constructing, rehabilitating, operating and
maintaining sewer mains under various infiltration levels over a 30-year life.
Ancillary costs such as infrastructure damage (e.g., roadway settlement) are not
included. The project was funded by participating industry members and the
Environmental Protection Agency Office of Wastewater through a grant to, and
administered by, the Fiberglass Tank & Pipe Institute. The model has been
calibrated with published data and may be used to compare different new,
rehabilitation and maintenance scenarios to identify the most cost effective
sewer main design. Design engineers may use the model to test alternative
designs and determine the lowest long term cost of a new or rehabilitation sewer
line project.
Infiltration Infrastructure Damage
The foregoing model does not include major life cycle costs associated with
infrastructure damage and a $10 million sinkhole and roadway rebuilding project
experienced in Houston, Texas. Design engineers may be able to gather historic
infrastructure damage data and apply the associated costs to future new and
rehabilitation projects.
Sdc 10/01/06 |